RFB-189-25 DJJ-Hopkinsville Group Home Improvements |
RFB-189-25 DJJ-Hopkinsville Group Home Improvements
Estimate:
$439,190.00
Estimated Length of Project:
240 (Substantial Completion) + 30 (Final Completion)
Volume One: Addition of an ADA accessible toilet and laundry room as well as removal of one office and creation of two offices within the building at an existing Group Home facility. The addition is a wood framed structure on a slab on grade. Finishes include painted gypsum board and ceramic tile. Work also includes installation of a larger primary entrance door for ADA accessibility. The existing office will be removed to accommodate access to the new laundry area. Two new offices will be created within the open area for staffing needs. Building PTAC unit will be remove and replaced with a VRF system to serve the HVAC needs of the building.
Volume Two: Work Area 1-Excavation & installation of a new drainage area/trench behind the existing facilities. Work to include earthwork, installation of new storm piping, concrete headwall, and drainage rock.
Work Area 2 – Removal of existing & installation of a new asphalt entrance. Work to include earthwork, paving, installing new storm piping, guardrails, and concrete headwalls.
Project Location: Hopkinsville