Corbin Independent Schools – Rebid for Painting Bid Package 0990 – Corbin High School Auxiliary Gym

Tue, Feb 18, 2025 9:49 AM

Corbin Independent Schools – Rebid for Painting Bid Package 0990 – Corbin High School Auxiliary Gym

Project Description: The Work consists of a new 13,853 square foot Auxiliary Gymnasium with
a 1,523 square foot equipment platform. The construction is primarily steel columns, beams
and joists with a 12-foot-tall brick and CMU cavity wall and the remainder of the exterior wall
to be constructed of cold formed metal framing with sheathing, insulation and metal wall
panels. The roof shall be constructed of a single-ply TPO roofing system over insulation and a
steel roof deck. Roof drainage shall be gutters and downspouts tied-into a below grade storm
drainage system. The building will house typical restrooms, storage room and a wood-floored
gymnasium with telescoping bleachers, basketball goals, volleyball standards and scoreboards.

The site work will consist of asphalt paving, concrete walks and storm drainage. The work will
occur on both sides of Early Street on the high school campus.

The HVAC shall be forced hot-air gas heat and air-conditioning with exterior pad-mounted
compressors and condensers. Electrical shall be a 600A, 3-phase service with energy efficient
LED lighting.

A new integrated fire alarm system, blue-light lock-down notification system and paging system
will be installed in the new auxiliary gymnasium as well as the existing High School, Area
Technology building, Career Center and fieldhouse all located on the same campus.

Project Location: Corbin, Kentucky