Grayson Utilities Commission – Contract 152-22-01 – Utilities Relocation KY1 at East Carter High School

Mon, Sep 8, 2025 2:02 PM

Grayson Utilities Commission – Contract 152-22-01 – Utilities Relocation KY1 at East Carter High School

The work to be bid is described as follows:

CONTRACT 152-22-01

Gas, water, and sewer utility line relocations consisting of approximately 2,400
linear feet of 3-inch, 6-inch, and 8-inch restrained joint, PVC pipe; approximately 1,700
linear feet of 2-inch and 4-inch welded steel pipe; approximately 1,025 linear feet of
1-inch, 4-inch, and 6-inch high-density polyethylene pipe and approximately 466 linear
feet of 12-inch steel casing pipe. Multiple individual driveway and road crossings for
these pipes and service lines will be required.

Project Location: Grayson, Kentucky

More Details

Go to Link: https://www.lynnimaging.com/bids/2025/09/08/grayson-utilities-commission-contract-152-22-01-utilities-relocation-ky1-at-east-carter-high-school/