Lynn Imaging Planroom

Logo

Phelps Freeburn WWTP Rehabilitation

Order
 001
 G-1
Cover Sheet
001-G-1_Cover_Sheet.tif
 002
 G-2
General Notes and Master Legend
002-G-2_General_Notes_and_Master_Legend.tif
 003
 C-1
Yard Piping Renovation and Site Plan
003-C-1_Yard_Piping_Renovation_and_Site_Plan.tif
 004
 P-1
Plant Influent Screen Chemical Storage Bldg
004-P-1_Plant_Influent_Screen_Chemical_Storage_Bldg.tif
 005
 P-2
SBR Renovation
005-P-2_SBR_Renovation.tif
 006
 P-3
SBR Renovation Details
006-P-3_SBR_Renovation_Details.tif
 007
 P-4
SBR Instrumentation
007-P-4_SBR_Instrumentation.tif
 008
 P-5
Aeration Renovation
008-P-5_Aeration_Renovation.tif
 009
 P-6
Sludge Transfer Renovation
009-P-6_Sludge_Transfer_Renovation.tif
 010
 P-7
Press Room Renovation Plan
010-P-7_Press_Room_Renovation_Plan.tif
 011
 P-8
Press Room Renovation Elevation
011-P-8_Press_Room_Renovation_Elevation.tif
 012
 P-10
Sludge Press Wash Water Return
012-P-10_Sludge_Press_Wash_Water_Return.tif
 013
 P-10
UV and Liquid Chlorine Disinfection Renovation
013-P-10_UV_and_Liquid_Chlorine_Disinfection_Renovation.tif
 014
 D-1
Bedding and Backfill Details
014-D-1_Bedding_and_Backfill_Details.tif
 015
 D-2
Erosion Control and Drainage Details
015-D-2_Erosion_Control_and_Drainage_Details.tif
 016
 D-3
Sanitary Sewer Manhole Details
016-D-3_Sanitary_Sewer_Manhole_Details.tif
 017
 D-4
Master Meter Station and Pipe Details
017-D-4_Master_Meter_Station_and_Pipe_Details.tif
 018
 D-5
Pipe Encasement Details
018-D-5_Pipe_Encasement_Details.tif
 019
 A-1
Chemical Storage Building Plan
019-A-1_Chemical_Storage_Building_Plan.tif
 020
 A-2
Chemical Storage Building Sections
020-A-2_Chemical_Storage_Building_Sections.tif
 021
 A-3
Chemical Storage Building Details
021-A-3_Chemical_Storage_Building_Details.tif
 022
 A-4
Chemical Storage Door Details
022-A-4_Chemical_Storage_Door_Details.tif
 023
 A-5
Chemical Storage Roll Up Door Details
023-A-5_Chemical_Storage_Roll_Up_Door_Details.tif
 024
 E-1
Electrical Site Plan and Riser Diagram
024-E-1_Electrical_Site_Plan_and_Riser_Diagram.tif
 025
 E-2
Plant Influent Screen Chem Storage Bldg Elec Plan
025-E-2_Plant_Influent_Screen_Chem_Storage_Bldg_Elec_Plan.tif
 026
 E-3
SBR Renovation Electrical Plan
026-E-3_SBR_Renovation_Electrical_Plan.tif
 027
 E-4
Sludge Transfer Electrical Plan Renovation
027-E-4_Sludge_Transfer_Electrical_Plan_Renovation.tif
 028
 E-5
Press Room Renovation Electrical Plan
028-E-5_Press_Room_Renovation_Electrical_Plan.tif
 029
 E-6
Decant Pump Station Elec Plan UV Demolition
029-E-6_Decant_Pump_Station_Elec_Plan_UV_Demolition.tif