Roof Replacement National Guard Armory
RFB 162-11
The work includes the removal and replacement of all built-up roofing, insulation and
flashings. It shall be noted that the existing aluminum counter flashing and parapet cap
flashing shall be removed and re-installed after the new roofing system is completed.
The existing ribbed metal decking shall remain. The main body of the roofing area has
a slope build to it, with the smaller, upper foyer decking being level. Standard straight
insulation shall be used, except on the upper foyer and the crickets/saddles shown on
the roof plan. These areas require tapered insulation with the desired elevations above
the roof as shown on the roof plans. The roof contains approximately 90 squares. The
small roof canopy over the front entrance requires new treated plywood roof decking
with a comparable roofing system with the addition of a sheathing membrane. This roof
requires new copper integral gutters and exposed downspouts.
Frankfort, KY.